Common problem

COMMON PROBLEM

4、 Comparison between spiral bite steel plate bin and bolt assembly bin

Date:2022-03-20   Visits:1191

Comparison between spiral bite steel plate silo and bolt assembly Silo:

project  Bolt assembly bin  Spiral bite steel plate warehouse

one  Warehouse form  Bolt assembly and manual connection on site  Spiral bite, automatic lifting, on-site mechanized operation

two Ф 11*H13. Material comparison of 51 meter silo  100g / m2 cold galvanized steel sheet  275 g / m2 double-sided high-quality hot-dip galvanized steel plate

Cylinder wall plate  4.51m 1.2mm plate  5.0m 2.0mm plate

1.12M 1.5mm plate  5.0m 2.5mm plate

3.37M 2.0mm plate  3.51M 3.0mm plate

2.25m 2.5mm plate

2.25m 3.0mm plate

Silo roof  0.6mm plate  1.2mm thick 275 g / m2 double-sided high-quality hot-dip galvanized steel plate

Frameless  The skeleton is No. 5 channel steel, with a total of 32 umbrella shaped layout

Column inside cylinder  2m 2mm plate  Column A: 8-row channel steel

5.5m 2mm plate  [10 #6m, [8 #7.51m]

2m 2.5mm plate  Column B: 24 row channel steel

2m 3.5mm plate  [10 #3m, [8 #3m, [6.3 #4m]

2m 4.0mm plate

The above is plate bending  The above is the national standard channel steel of Jinan Iron and Steel Co., Ltd

Warehouse door, enclosure and ladder  Painting treatment after processing  Hot dip galvanizing treatment

Bolt strength grade  Grade 8.8  There is no need for bolt connection and mechanical engagement on site to prevent bolt stress fracture

three  Material requirements  Galvanized plate (100g / m2), easy to rust, three years  Strict (double-sided hot-dip galvanized sheet 275g / m2 galvanized sheet sgh340, sgh400, sgh440)

Steel plate thickness  Thin (0.4-3mm)  Thickness (2.0-4.0mm)

four  Utilization coefficient of steel plate  87%  63%

five  Installation Machinery  Simple, manually pull the hoist on site for a long time, and the single warehouse is 10 days  Complex, the unit with the latest imported technology from Europe in 2008 is fully automatic, the construction period is short, and the single warehouse is 6 days

six  Sealing performance  Poor, the sealing rubber gasket is easy to aging, water seepage and difficult to be found. There are materials hanging on the wall due to moisture, which is easy to produce insects  Good, no water leakage, fumigation system can be installed

seven  strength  Poor, the cylinder bolt strength is not enough, easy to break, and the column is bent with thin plate  Strengthen the strength of the vertical five-way channel with the national standard thickness

eight  Wind and earthquake resistance  Poor, there are warehouse turnover accidents in China every year  OK, it can resist earthquakes above magnitude 8 and typhoons above magnitude 12

nine  Waterproof and leak proof  Poor, there are accumulated errors in punching and installation between bolt holes, which need to be corrected on site. There are cracks in punching, resulting in stress and metal fatigue  Good, never leaking, can store sewage, grease and other liquids

ten  life  The bolt strength is grade 8.8, and it is easy to break. The bolt and rubber pad need to be replaced within 5 years, which is easy to rust  The normal service life of the industrial zone is more than 30 years and does not need any maintenance


Last:5、 Silo construction -- comparison between steel silo and concrete silo

Next:3、 Calculation method of grain steel silo capacity